SKIMS Retail Rollout — Program Tracker
Week of Jul 27, 2026
Compared to Jul 27 18:09 UTC build (v2.1.232)
Last updated: Jul 27, 2026 19:08 UTC · v2.1.233 · 0 new changes since v2.1.232 — stable re-verification; all 20 projects re-pulled per-project (never by position) and matched prior values milestone-for-milestone. Recent movers from v2.1.229 hold and retain their date-change badges: City Creek & Seaport (+21d), La Cantera (+14d), Las Vegas North (GC SC +4d / 9wk XF +7d), Country Club Plaza (CS +9d, GC SC/H/O/GO/XF +14d). Source files intact this refresh (0 NUL bytes, ends with </html>, JSON parses, 20 projects) · Bellevue & Brickell still Tier-2 (no individual sheet)
Overall Capex Health — FY26 Portfolio
20
Active Projects
$3.0M
Under Approved Capex (net)
7
Projects Over Budget
9
On / Under Budget
6
8wk XF Notices Due ≤30 Days
5
Schedule Changes This Refresh
Excess Approved Funds
Total Finance Approved
Total Contingency
Total Projected Cost
Budget Composition — 15 USD Projects
9 On/Under Budget 7 Over Budget · Last budget edit: Marshall Ryan · Mar 23, 2026
⚑ Attention: 0 new schedule changes this refresh (Jul 27, 15:10 UTC) — stable re-verification; all 20 projects re-pulled per-project and matched prior values milestone-for-milestone.  ·  Recent movers from the 15:00 UTC build (v2.1.229) still hold: City Creek & Seaport (+21d), La Cantera (+14d), Las Vegas North (GC SC +4d / 9wk XF +7d), Country Club Plaza (CS +9d, back-half +14d). All verified per-project against each individual sheet by Key Milestone task name.  ·  Recent movers holding: Mall at Millenia (2027, GO Oct 28, 2027), Somerset Collection (GO Feb 11, 2027), Broadway Plaza (GO Oct 23), Americana at Brand (GO Aug 14).  ·  Next grand openings: Fashion Valley & Southpark (Jul 31, 2026).  ·  Americana at Brand overrun: +$658K (largest in portfolio).
Active Projects — Smartsheet Schedule Order
King Street
Charleston, SC
Design 2.0 · 7,100 SF
✓ Opened Apr 3 On Budget 8wk XF ✓ Done
Key Milestones No schedule changes this week
Construction Start
Dec 1, 2025
GC Substantial Completion
Mar 12, 2026
H/O to Ops
Mar 30, 2026 ✓ Done
Grand Opening
Apr 3, 2026
8wk XF Notice
Feb 2, 2026 — ✓ Complete
Cross-functional partners confirmed; turnover date locked at Mar 30
Budget
Finance Approved
$4,130,000
Current Contracted
$2,984,701
Variance
−$1,029,003
Paid to Date
$1,817,568
Contingency
$116,296
No WoW budget changes detected
H/O to Ops Mar 30 (complete). Grand Opening Apr 3 (today).
Woodbury Commons
Central Valley, NY
Outlet · 5,413 SF
On Schedule On Budget 8wk XF in 15 days
Key Milestones No schedule changes this week
Construction Start
Mar 17, 2026
GC Substantial Completion
Jun 1, 2026
H/O to Ops
Jun 14, 2026
Grand Opening
Jun 19, 2026
⚑ 8wk XF Notice — Due April 20, 2026 (15 days)
Action Required: Confirm turnover date with XF partners by Apr 20
Note: Experiencing some minor lag in jurisdictional review relative to 8wk anticipated
Budget
Finance Approved
$3,500,000
Current Contracted
$2,307,522
Variance
−$963,541
Paid to Date
$232,301
Contingency
$228,937
No WoW budget changes detected
Village at Corte Madera
Corte Madera, CA
Design 2.2 VEVE · 3,628 SF
✓ Opened Jun 26 Over Budget 8wk XF ✓ Past
Key Milestones No new schedule changes this refresh
Construction Start
Feb 23, 2026
GC Substantial Completion
Jun 8, 2026
H/O to Ops
Jun 22, 2026
Grand Opening
Jun 26, 2026 ✓
⚑ 8wk XF Notice — Issued April 27, 2026 ✓
Grand Opening date (Jun 26) has now passed. Milestones held from last refresh.
The +7d H/O & Grand Opening slip from the Jun 16 refresh held with no further movement; GC SC held at Jun 8. Grand Opening date of Jun 26 has now passed — confirm final open status and turnover with Ops.
Budget
Finance Approved
$2,498,000
Current Contracted
$2,550,997
Variance
+$163,415
Paid to Date
$804,056
Contingency
$110,418
No WoW budget changes detected
⚑ Grand Opening date (Jun 26) has now passed; the prior +7d slip held with no further movement. Confirm final open/turnover status with Ops; project remains over budget.
Fashion Valley
San Diego, CA
Design 2.0 · 6,132 SF
Schedule Slip +7d On Budget
Key Milestones ⚠ GC Substantial Completion slipped +7d this refresh
Construction Start
Mar 9, 2026
GC Substantial Completion
Jul 10Jul 17, 2026+7d
H/O to Ops
Jul 20Jul 27, 2026+7d
Grand Opening
Jul 24Jul 31, 2026+7d
8wk XF Notice — May 25Jun 1, 2026+7d
N/A — already issued
GC Substantial Completion slipped +7d this refresh (Jul 10 → Jul 17 = Under Construction task End Date); Construction Start held at Mar 9. H/O (Jul 27), Grand Opening (Jul 31) and XF (Jun 1) held with no further movement after their prior +7d back-half slip. Re-pulled from the Fashion Valley individual sheet by Key Milestone task name.
Budget
Finance Approved
$4,600,000
Current Contracted
$3,273,292
Variance
−$1,326,708
Paid to Date
$873,767
Contingency
$0
No WoW budget changes detected
Fashion Square
Scottsdale, AZ
Design 2.1 VE · 3,500 SF
⚡ Pulled In 7d Over Budget
Key Milestones ⚡ H/O, Grand Opening & XF pulled in −7d this refresh
Construction Start
Mar 9, 2026
GC Substantial Completion
Jun 29, 2026
H/O to Ops
Jul 6Jun 29, 2026-7d
Grand Opening
Jul 10Jul 3, 2026-7d
8wk XF Notice — May 11May 4, 2026-7d
N/A — already issued
H/O, Grand Opening and XF each pulled in −7d this refresh (H/O Jul 6 → Jun 29; Grand Opening Jul 10 → Jul 3; XF May 11 → May 4). Construction Start (Mar 9) and GC SC (Jun 29) held. Re-pulled from the Fashion Square individual sheet by Key Milestone task name.
Budget
Finance Approved
$2,245,000
Current Contracted
$2,330,880
Variance
+$311,740
Paid to Date
$411,270
Contingency
$225,861
No WoW budget changes detected
Americana at Brand
Glendale, CA
Design 2.1 VE · 7,089 SF
Schedule Slip Over Budget
Key Milestones ⚠ Schedule slipped +21–31d this cycle (late permit issuance)
Construction Start
Mar 16, 2026
GC Substantial Completion
Jul 3Aug 3, 2026+31d
H/O to Ops
Jul 20Aug 10, 2026+21d
Grand Opening
Jul 24Aug 14, 2026+21d
8wk XF Notice — May 25Jun 15, 2026+21d
18 days out
Late permit issuance has slipped XF by 3 weeks; downstream milestones shifted in parallel (GC SC widened by 10 add'l days). Reconfirm GC commitment to revised milestones.
Budget
Finance Approved
$3,300,000
Current Contracted
$3,613,334
Variance
+$658,228
Paid to Date
$675,833
Contingency
$344,894
No WoW budget changes detected
⚑ Largest overrun in portfolio (+$658K) AND new +21–31d schedule slip from late permit issuance. Reconfirm GC commitment to revised milestones; review scope change log.
Regent Street
London, UK
Flagship · 12,122 SF · GBP
On Schedule On Budget (£)
Key Milestones ⚡ H/O reverted +1d (prior cycle)
Construction Start
Jan 7, 2026
GC Substantial Completion
Jun 19, 2026
H/O to Ops
Jul 8Jul 9, 2026+1d
Grand Opening
Jul 23, 2026
8wk XF Notice — May 13, 2026
38 days out
Budget (GBP — tracked separately)
Finance Approved
£7,200,000
Current Contracted
£6,596,827
Variance
−£132,493
Paid to Date
£1,420,793
Contingency
£470,680
No WoW budget changes detected
Southpark
Charlotte, NC
Design 2.1 VE · 5,572 SF
Schedule Slip +7d Over Budget
Key Milestones ⚠ GC Substantial Completion slipped +7d this refresh
Construction Start
Mar 23, 2026
GC Substantial Completion
Jul 10Jul 17, 2026+7d
H/O to Ops
Jul 24Jul 27, 2026+3d
Grand Opening
Jul 31, 2026
8wk XF Notice — Jun 1, 2026
57 days out
GC Substantial Completion slipped +7d this refresh (Jul 10 → Jul 17 = Under Construction task End Date). Construction mobilized Mar 23. H/O Jul 27 and GO Jul 31 held. XF notice Jun 1. Re-pulled from the Southpark individual sheet by Key Milestone task name.
Budget
Finance Approved
$3,324,000
Current Contracted
$3,102,236
Variance
+$85,144
Paid to Date
$114,417
Contingency
$306,907
No WoW budget changes detected
City Creek Center
Salt Lake City, UT
Design 2.1 VE · 4,167 SF
Schedule Slip +21d Over Budget
Key Milestones ⚠ H/O, Grand Opening & XF slipped +21d this refresh
Construction Start
May 25, 2026
GC Substantial Completion
Aug 28, 2026
H/O to Ops
Sep 14Oct 5, 2026+21d
Grand Opening
Sep 18Oct 9, 2026+21d
8wk XF Notice — Jul 20Aug 10, 2026+21d
14 days out
Back-half slip this refresh: H/O Sep 14 → Oct 5 (+21d), Grand Opening Sep 18 → Oct 9 (+21d), 8wk XF Jul 20 → Aug 10 (+21d). Construction window held at 5/25 → 8/28. Re-pulled from the City Creek individual sheet by Key Milestone task name.
Budget
Finance Approved
$2,476,878
Current Contracted
$2,281,886
Variance
+$33,196
Paid to Date
$35,895
Contingency
$228,189
No WoW budget changes detected · Smallest overrun in portfolio — may be resolvable
La Cantera
San Antonio, TX
Design 2.1 VE · 3,874 SF
Schedule Slip +14d Over Budget
Key Milestones ⚠ H/O, Grand Opening & XF slipped +14d this refresh
Construction Start
Jun 1, 2026
GC Substantial Completion
Sep 7, 2026
H/O to Ops
Sep 21Oct 5, 2026+14d
Grand Opening
Sep 25Oct 9, 2026+14d
8wk XF Notice — Jul 27Aug 10, 2026+14d
14 days out
Back-half slip this refresh: H/O Sep 21 → Oct 5 (+14d), Grand Opening Sep 25 → Oct 9 (+14d), 8wk XF Jul 27 → Aug 10 (+14d). Construction window held at 6/1 → 9/7. Re-pulled from the La Cantera individual sheet by Key Milestone task name.
Budget
Finance Approved
$2,464,458
Current Contracted
$2,333,623
Variance
+$102,528
Paid to Date
$35,385
Contingency
$233,362
No WoW budget changes detected
Broadway Plaza
Walnut Creek, CA
Design 2.1 VE · 4,500 SF
Schedule Slip — Holding Over Budget
Key Milestones Prior +11–14d slip holding — no new changes this refresh
Construction Start
Jun 15, 2026
GC Substantial Completion
Oct 2, 2026
H/O to Ops
Oct 16, 2026
Grand Opening
Oct 23, 2026
8wk XF Notice — Aug 21, 2026
46 days out
The +11–14d slip from the Jun 16 refresh held with no further movement this refresh (Grand Opening Oct 23). GC SC = Construction-task End Date (Oct 2). Reconfirm GC commitment to the revised path and verify the Aug 21 XF date.
Budget
Finance Approved
$3,600,000
Current Contracted
$3,391,086
Variance
+$123,010
Paid to Date
$143,459
Contingency
$331,924
No WoW budget changes detected
Las Vegas North Outlets
Las Vegas, NV
Outlet · 5,811 SF
Schedule Slip +4–7d On Budget
Key Milestones ⚠ GC SC +4d and 9wk XF +7d this refresh (CS/H/O/GO holding)
Construction Start
Jun 15, 2026
GC Substantial Completion
Aug 31Sep 4, 2026+4d
H/O to Ops
Sep 21, 2026
Grand Opening
Sep 25, 2026
9wk XF Notice — Jul 20Jul 27, 2026+7d
Due today
GC SC slipped +4d (Aug 31 → Sep 4) and the 9wk XF moved later +7d (Jul 20 → Jul 27, now due today), reversing the prior cycle's pull-in. Construction Start (Jun 15), H/O (Sep 21) and Grand Opening (Sep 25) held. Re-pulled from the Las Vegas North Outlets individual sheet by Key Milestone task name (GC SC = Construction task End Date).
Budget
Finance Approved
$3,585,086
Current Contracted
$3,189,249
Variance
−$76,912
Paid to Date
$97,130
Contingency
$318,925
No WoW budget changes detected
⚑ GC SC slipped +4d (now Sep 4) and the 9wk XF moved +7d (now Jul 27, due today) this refresh; CS (Jun 15), H/O (Sep 21) and Grand Opening (Sep 25) held. Still on budget. Confirm the Jul 27 XF readiness with XF partners.
Seaport
Boston, MA
Design 2.2 VEVE · 3,902 SF
Schedule Slip +21d On Budget
Key Milestones ⚠ H/O, Grand Opening & XF slipped +21d this refresh
Construction Start
May 11, 2026
GC Substantial Completion
Aug 28, 2026
H/O to Ops
Sep 14Oct 5, 2026+21d
Grand Opening
Sep 18Oct 9, 2026+21d
8wk XF Notice — Jul 20Aug 10, 2026+21d
14 days out
Back-half slip this refresh: H/O Sep 14 → Oct 5 (+21d), Grand Opening Sep 18 → Oct 9 (+21d), 8wk XF Jul 20 → Aug 10 (+21d). Construction window held at 5/11 → 8/28. Re-pulled from the Seaport individual sheet by Key Milestone task name. Discuss the budgeted opening date with Finance.
Budget
Finance Approved
$3,573,000
Current Contracted
$3,128,097
Variance
−$157,334
Paid to Date
$123,250
Contingency
$287,569
No WoW budget changes detected
Prudential Center
Boston, MA
Design 2.1 VE · 5,000 SF
On Schedule On Budget
Key Milestones ✓ Corrected to true 2026 schedule this cycle
Construction Start
Jun 8, 2026
GC Substantial Completion
Sep 25, 2026
H/O to Ops
Oct 12, 2026
Grand Opening
Oct 16, 2026
8wk XF Notice — Aug 17, 2026
63 days out
Data correction: prior cycles displayed erroneous 2027 dates (a positional-mapping artifact that duplicated Ala Moana's schedule). Restored to Prudential's true 2026 milestones from its individual project sheet — Grand Opening Oct 16, 2026. Clarify with ADG the contents of bid set.
Budget
Finance Approved
$4,530,000
Current Contracted
$3,999,023
Variance
−$16,735
Paid to Date
$126,353
Contingency
$514,242
No WoW budget changes detected
Country Club Plaza
Kansas City, MO
Design 2.1 VE · 5,300 SF
Schedule Slip +9–14d On Budget
Key Milestones ⚠ Schedule slipped again +9–14d (CS, GC SC, H/O, GO, XF) this refresh
Construction Start
Jul 20Jul 29, 2026+9d
GC Substantial Completion
Oct 23Nov 6, 2026+14d
H/O to Ops
Nov 9Nov 23, 2026+14d
Grand Opening
Nov 13Nov 27, 2026+14d
8wk XF Notice — Sep 14Sep 28, 2026+14d
63 days out
Schedule slipped again this refresh: Construction Start Jul 20 → Jul 29 (+9d), GC SC Oct 23 → Nov 6 (+14d), H/O Nov 9 → Nov 23 (+14d), Grand Opening Nov 13 → Nov 27 (+14d), XF Sep 14 → Sep 28 (+14d). The Construction task Start moved to Jul 29 on the sheet (Possession Date also Jul 29), so Construction Start now reads Jul 29 (window 7/29 → 11/6). Grand Opening now trails the ~Oct 1 budgeted opening by nearly two months; reconfirm the revised path with the GC and reset XF readiness to Sep 28.
Budget
Finance Approved
$3,498,843
Current Contracted
$3,015,036
Variance
−$182,303
Paid to Date
$2,500
Contingency
$301,504
No WoW budget changes detected
Mall at Millenia
Orlando, FL
New for FY26 Pipeline
Schedule Slip +294–307d On Budget
Key Milestones ⚠ Whole schedule pushed ~10 months to 2027 this refresh
Construction Start
Sep 1, 2026Jul 5, 2027+307d
GC Substantial Completion
Dec 18, 2026Oct 8, 2027+294d
H/O to Ops
Jan 1, 2027Oct 22, 2027+294d
Grand Opening
Jan 7, 2027Oct 28, 2027+294d
8wk XF Notice — Nov 6, 2026Aug 27, 2027+294d
410 days out
Whole schedule pushed out ~10 months this refresh: Construction Start Sep 1, 2026 → Jul 5, 2027 (+307d), GC Substantial Completion Dec 18, 2026 → Oct 8, 2027 (+294d), H/O to Ops Jan 1 → Oct 22, 2027 (+294d), Grand Opening Jan 7 → Oct 28, 2027 (+294d), 8wk XF Nov 6, 2026 → Aug 27, 2027 (+294d). Possession Date on the individual sheet now reads Jul 1, 2027 (was the ~Jul 1, 2026 early-possession option Dan was confirming). Re-pulled from the Mall at Millenia individual sheet 1164764706197380 by Key Milestone task name (GC SC = Construction task End Date).
Budget
Finance Approved
TBD
Current Contracted
TBD
Variance
Budget data pending — newly added to dashboard
Somerset Collection
Troy, MI (Detroit)
2027 Pipeline · TBD SF
Schedule Slip +10-18d 2027 Pipeline
Key Milestones ⚠ All milestones slipped +10–18d last refresh — now holding
Construction Start
Sep 25Oct 5, 2026+10d
GC Substantial Completion
Jan 7Jan 22, 2027+15d
H/O to Ops
Jan 21Feb 8, 2027+18d
Grand Opening
Jan 27Feb 11, 2027+15d
8wk XF Notice — Nov 26Dec 14, 2026+18d
154 days out
Whole schedule slipped last refresh (v2.1.194), now holding: Construction Start Sep 25 → Oct 5 (+10d), GC Substantial Completion Jan 7 → Jan 22 (+15d), H/O to Ops Jan 21 → Feb 8 (+18d), Grand Opening Jan 27 → Feb 11, 2027 (+15d), 8wk XF Nov 26 → Dec 14 (+18d). Re-pulled from the Somerset Collection individual sheet 8631528165691268 by Key Milestone task name (GC SC = Construction task End Date).
Budget
Status
Pre-budget / planning
Finance Approved
TBD
Current Contracted
Paid to Date
Contingency
Budget tracking begins at GC bid/award
Ala Moana
Honolulu, HI
2027 Pipeline · TBD SF
Pre-Construction 2027 Pipeline
Key Milestones 2027 pipeline — schedule from individual sheet
Construction Start
Feb 15, 2027
GC Substantial Completion
Jun 7, 2027
H/O to Ops
Jun 21, 2027
Grand Opening
Jun 25, 2027
8wk XF Notice — Apr 26, 2027
323 days out
Possession Date Jan 1, 2027. Permit review through Feb 2027.
Budget
Status
Pre-budget / planning
Finance Approved
TBD
Current Contracted
Paid to Date
Contingency
Budget tracking begins at GC bid/award
Bellevue Square
Bellevue, WA
2027 Pipeline · TBD SF
Pre-Construction 2027 Pipeline
Key Milestones ▲ Schedule pulled in −29d (CS, GC SC, H/O, GO) this refresh
Construction Start
Mar 4Feb 3, 2027-29d
GC Substantial Completion
Jun 23May 25, 2027-29d
H/O to Ops
Jul 8Jun 9, 2027-29d
Grand Opening
Jul 14Jun 15, 2027-29d
8wk XF Notice — TBD
milestone not yet defined in master schedule
APPROVED DEAL. Entire schedule pulled in −29d this refresh (CS Mar 4 → Feb 3; GC SC Jun 23 → May 25; H/O Jul 8 → Jun 9; Grand Opening Jul 14 → Jun 15, 2027). Re-pulled from the 2027 Pipeline Planning Schedule master (parent row "Bellevue Square - Bellevue, WA"); GC SC = "Construction" task Finish. Possession Q1 2027; 22wk fixture period TBC.
Budget
Status
Pre-budget / planning
Finance Approved
TBD
Current Contracted
Paid to Date
Contingency
Budget tracking begins at GC bid/award
Brickell
Miami, FL
2027 Pipeline · TBD SF
Pre-Construction 2027 Pipeline
Key Milestones 2027 pipeline — schedule from 2027 master schedule
Construction Start
May 3, 2027
GC Substantial Completion
Aug 20, 2027
H/O to Ops
Sep 6, 2027
Grand Opening
Sep 10, 2027
8wk XF Notice — TBD
milestone not yet defined in master schedule
APPROVED DEAL. Q2 2027 possession (DH file 3.23). 22wk fixture period TBC.
Budget
Status
Pre-budget / planning
Finance Approved
TBD
Current Contracted
Paid to Date
Contingency
Budget tracking begins at GC bid/award
Completed Projects
Cherry Creek
Denver, CO
Design 2.0 · 5,372 SF
✓ Opened Feb 17, 2026 Under Budget
Final Milestone Dates
Construction Start
Nov 3, 2025
8wk XF Notice
Dec 18, 2025
H/O to Ops
Feb 12, 2026
Grand Opening
Feb 17, 2026
Final Budget
Finance Approved
$3,465,000
Final Contracted
$2,695,194
Variance
−$769,806
Paid to Date
$2,062,962
Follow-up Questions
Action Items & Questions — Week of Jul 27, 2026
1 Village at Corte MaderaGrand Opening date (Jun 26) has now passed; the +7d slip from the Jun 16 refresh held with no further movement. Action: confirm final open/turnover status with Ops and close out; project remains over budget (+$163K).
2 Imminent XF NoticesLas Vegas North Outlets 9wk XF is due today (Jul 27). Three 8wk XF notices land Aug 10: City Creek Center, Seaport, and La Cantera (all slipped +14–21d this refresh). Prudential Center follows Aug 17 and Broadway Plaza Aug 21. Confirm turnover readiness with XF partners across all six over the coming weeks.
3 Americana at Brand — Largest overrun in portfolio (+$658K) AND new +21–31d schedule slip from late permit issuance. XF Notice: May 25 → Jun 15 (+21d); GC SC: Jul 3 → Aug 3 (+31d); GO: Jul 24 → Aug 14 (+21d). Reconfirm GC commitment to revised milestones; press for clarity on permit timeline and downstream impact to operational readiness.
4 Country Club Plaza — ⚠ Schedule slipped again +9–14d this refresh: Construction Start Jul 20 → Jul 29 (+9d), GC SC Oct 23 → Nov 6 (+14d), H/O Nov 9 → Nov 23 (+14d), Grand Opening Nov 13 → Nov 27 (+14d), XF Sep 14 → Sep 28 (+14d). The Construction task Start moved to Jul 29 on the sheet (Possession Date also Jul 29), so CS now reads Jul 29. Grand Opening (Nov 27) trails the ~Oct 1 budgeted opening by nearly two months. Action: reconfirm the revised path with the GC and reset XF readiness to Sep 28.
5 Mall at Millenia — ⚠ Whole schedule pushed ~10 months to 2027 this refresh (+294–307d): Construction Start Sep 1, 2026 → Jul 5, 2027, GC Substantial Completion Dec 18, 2026 → Oct 8, 2027, H/O to Ops Jan 1 → Oct 22, 2027, Grand Opening Jan 7 → Oct 28, 2027, 8wk XF Nov 6, 2026 → Aug 27, 2027. The individual sheet's Possession Date now reads Jul 1, 2027 (previously the ~Jul 1, 2026 early-possession option Dan was confirming), so the early-possession scenario appears off the table. Action: confirm the revised 2027 program with Dan/GC, and provide Finance Approved and current contracted budget figures (still pending) for the next refresh.
6 Unmatched Smartsheet row — Smartsheet contains an ACTUAL row (CS May 26, GO Oct 2) that does not map to any of the 16 tracked projects. Still present as of this refresh. Confirm whether this represents a new project to be added to the dashboard or a placeholder row.
7 Schedule movement this refresh5 projects moved, all verified directly against each project's individual sheet by Key Milestone task name (never by position). City Creek Center and Seaport back-half slipped +21d (H/O, Grand Opening & 8wk XF; GO Oct 9). La Cantera back-half slipped +14d (GO Oct 9). Las Vegas North GC SC +4d (Sep 4) and 9wk XF +7d (Jul 27, due today); CS/H/O/GO held. Country Club Plaza slipped +9–14d (Construction Start Jul 29; GO Nov 27). The other 15 tracked projects re-pulled per-project and matched prior values milestone-for-milestone (Bellevue Square & Brickell still master-sourced Tier-2). Note: GC SC is sourced from each individual sheet's Construction/Under Construction task End Date.