Action Items & Questions — Week of Sep 21, 2026
1
Las Vegas North Outlets — Opens Fri Sep 25, 2026 — today. H/O to Ops completed Mon Sep 21 and GC Substantial Completion landed Sep 4; both re-confirmed from source this cycle. This is the last scheduled refresh before the store opens. Action: confirm final turnover walk and opening-day readiness with Ops and the GC.
2
Country Club Plaza — Back half slipped +14d this refresh. GC Substantial Completion Nov 6 → Nov 20, H/O to Ops Nov 16 → Nov 30, Grand Opening Nov 20 → Dec 4, and the 8wk XF notice Sep 21 → Oct 5. Construction Start holds at Aug 3. The XF notice had been logged as issued Mon Sep 21, so the Ops readiness clock needs to be reset to Oct 5. Action: confirm with the GC what pushed the Construction task end out two weeks, and whether the Sep 21 notice to Ops should be formally re-issued. (Prudential Center’s Sep 21 notice stands; H/O Nov 16 / GO Nov 20 held.)
3
Broadway Plaza — Next 8wk XF notice: Mon Oct 5, 10 days out — now shared with Country Club Plaza, which slipped into the same date this refresh. Grand Opening Dec 4 still carries the cumulative +42 to +45d of back-half slip logged in late August and early September; Construction Start (Jun 15) and GC Substantial Completion (Nov 27) have held every cycle since. Action: confirm the turnover plan between GC SC and H/O, where the entire push sits.
4
Americana at Brand — Largest overrun in the portfolio (+$658K). The store opened Aug 14 on the revised dates following the late-permit slip. Action: close out the project financially and confirm the final cost position with Finance.
5
Mall at Millenia — Schedule is settled on the accelerated 2027 path pulled in at v2.1.267 (Construction Start Feb 1, GC SC Jun 4, H/O Jun 4, Grand Opening Jun 10, all 2027) and has not moved since. Budget figures are still pending. Action: provide Finance Approved and current contracted amounts so the card can come off placeholder values.
6
Bellevue Square & Brickell — Both remain Tier-2, sourced from parent rows in the 2027 Pipeline master; neither has graduated to its own schedule sheet. Bellevue’s +32 to +34d slip (first seen Sep 14) is now confirmed on a fourteenth independent pull and is settled. Neither project has an 8wk XF row in the master, so those countdowns show TBD. Note: the Smartsheet sheet-name search is declined on every unattended run, so graduation to Tier-1 can only be inferred from their still being parent-row blocks. Approving that one search for scheduled runs would close the last standing gap.
7
Schedule movement this refresh — 4 changes, all on Country Club Plaza (+14d back half), on a complete 20-of-20 cycle. Every other milestone on the other 19 projects was re-read from its own source and matched its stored value exactly. Country Club Plaza’s Construction Start was re-verified at Aug 3 from the Construction task, never from the Possession Date. No positional mapping was used anywhere.
8
Housekeeping — XF countdowns corrected — The per-card “days out” figures had drifted, each frozen at whichever cycle last edited that card: Americana still read “18 days out” for a notice issued Jun 15, Las Vegas North Outlets read “Due today” for Jul 27, and Seaport read “8 days ago” for Aug 24. The underlying milestone dates were always correct — only the countdown text was stale. All of them have been recomputed against today, and the “due within 30 days” tile drops from 3 to 1 now that the Sep 21 pair has issued.