Action Items & Questions — Week of March 30
1
King Street — H/O to Ops today (Mar 30). Grand Opening in 4 days (Apr 3). Confirm final punch list cleared, fixture deliveries complete, and LL sign-offs received. Ops move-in underway.
✓
Southpark — CS confirmed Mar 27 (3 days ago, on schedule). GC now mobilized — confirm site access and early work proceeding. Downstream milestones unchanged: GC SC Jul 9, H/O Jul 24, GO Jul 30.
2
Woodbury Commons + Corte Madera — 8wk XF Notice due April 20 (21 days). Confirmed turnover date locked for both? Woodbury has jurisdictional review lag; Corte Madera TI permit still outstanding with outside risk to Apr 6.
3
City Creek Center — Delay from prior week (+8–10d) now baselined: CS May 26, GC Sep 14, GO Oct 2. Confirm 18-week construction duration with GC and verify no further schedule risk.
4
Americana at Brand — Largest overrun in portfolio (+$658K). Construction at-risk mobilized 3/16. What's driving the overrun — scope changes, GC overages, or design revisions? Permit status?
5
Mall at Millenia — Budget data still pending. Please confirm Finance Approved amount and current contracted figures for next refresh.